 |
Technical Paper T-140
Heating and Storing Asphalt at HMA Plants
Publication No. T-140
download T-140 in PDF format
Pages: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 15, 16, 17, 18, 19, 20, 21
Heat requirements
The amount of heat (Btu/hr) needed for heating asphalt and components at an asphalt plant is known as heat demand. An estimate of the heat demand should be made when purchasing new asphalt heating equipment or upgrading old equipment. The estimate can provide important information for selecting new equipment. Heat demand is the key to choosing the appropriate capacity of the heating equipment and can enable you to closely estimate fuel costs.
Your estimate should include every heated component (including asphalt piping, and hot oil piping) along with the Btu required to maintain them at a specific temperature. Be sure to include an appropriate amount of extra heat demand for raising the temperature of asphalt that you buy at a temperature lower than required for the mix. (This assumes that you must raise its temperature in order to use it.) Also allow for asphalt tanks and storage silos you plan to add in the foreseeable future. Add a safety margin of about 20 percent to the estimated demand to allow for unknowns and contingencies.
Figures 38, 39 and 40 show hourly and daily Btu usage for typical stationary, relocatable and portable plants. The total hourly usage can be used as a starting point for estimating heat demand for such plants. But remember that the totals in those figures is only a sum of the heat required for the components listed. Moreover, the total hourly usage does not include the extra heat needed during the first hour of a cold start, before heat from hot aggregate supplements heat of the hot oil system.
So, the heat demand for your plant should start with the hourly usage for all of its specific components. To that you should add extra heat for startup plus all of the factors mentioned earlier. It would be virtually impossible to accurately calculate all those factors because of unknowns. So, it is appropriate to make a judgement based on experience.
We recommend increasing the total hourly usage by a factor of about 4 times. In some cases the factor could be up to 10 times.
Thus, we recommend a heater with an output of 2 million Btu/hour for the stationary plant described in Figure 38. We recommend a 1.2 milion Btu/hour heater for the relocatable plant described in Figure 39. And we recommend a 1million Btu/hour heater for the portable plant described in Figure 40.
Figure 41 shows heat demands for key components of drum mix plants and batch plants. Figure 42 shows the heat demands for various other components of a plant. Heat demands are shown for pre-startup and run. In both cases this is the heat loss that the hot oil system must replace.
Figure 41. Heat Demands For Key Components.
| Equipment |
Btu per Hour |
| Pre-Startup |
Run |
| Double Barrel Drum Mixer 7 x 35 ft (hot oil jacket) |
213,091 |
35,200 |
| Double Barrel Drum Mixer 8 x 39 ft (hot oil jacket) |
215,929 |
38,640 |
| Double Barrel Drum Mixer 9 x 46 ft (hot oil jacket) |
349,270 |
43,520 |
| Metering Pkg, Drum Mix Plant, 100300 tph |
38,725 |
19,363 |
| Metering Pkg, Drum Mix Plant, 400600 tph |
50,171 |
25,085 |
| Weigh Bucket & Pugmill, 4,000 lb Batch Plant |
117,000 |
90,962 |
| Weigh Bucket & Pugmill, 6,000 lb Batch Plant |
135,000 |
93,184 |
| Weigh Bucket & Pugmill, 8,000 lb Batch Plant |
168,000 |
101,884 |
| Weigh Bucket & Pugmill, 10,000 lb Batch Plant |
214,000 |
111,230 |
| Weigh Bucket & Pugmill, 12,000 lb Batch Plant |
275,000 |
120,752 |
| Weigh Bucket & Pugmill, 14,000 lb Batch Plant |
351,000 |
131,156 |
| Weigh Bucket & Pugmill, 16,000 lb Batch Plant |
442,000 |
142,618 |
Figure 42. Heat Demands For Other Components.
| Equipment |
Btu per Hour |
| Pre-Startup |
Run |
| Asphalt Storage Silo, 100-Ton |
100,000 |
17,735 |
| Asphalt Storage Silo, 150-Ton |
150,000 |
21,635 |
| Asphalt Storage Silo, 200-Ton |
200,000 |
25,719 |
| Asphalt Storage Silo, 250-Ton |
250,000 |
30,590 |
| Asphalt Storage Silo, 300-Ton |
300,000 |
33,216 |
| Traverse conveyor, 24 inches x 14 ft-8 inches |
24,911 |
5,720 |
| Traverse conveyor, 36 inches x 16 ft-8 inches |
34,465 |
9,750 |
| Drag conveyor, 300 tph, 24 Inch width (per foot) |
3,736 |
390 |
| Drag conveyor, 400 tph, 36 Inch width, (per foot) |
4,377 |
585 |
| Drag conveyor, 500 tph, 42 Inch width, (per foot) |
4,698 |
683 |
| Heavy fuel preheater 1000 gal/hour |
3,593 |
336,709 |
| Silos have heated cones and gates, 6-inch sidewall insulation, 8-inch cone insulation. |
Pre-startup means that the plant is not running HMA. Thus, the hot oil system replaces virtually all of the heat lost. Run means that the plant is running HMA. Consequently, heat from the HMA replaces much of the heat lost, thereby reducing the load on the hot oil system.
The goal of carefully estimating the heat demand is to get a heater that is neither too small nor too large. Correctly estimating the demand will enable you to pick a heater of the optimum size. A properly sized heater runs about 75 percent of the time while the plant is operating. If the demand is significantly underestimated you will get a heater that is too small to handle the plant temperature requirements. Moreover, heaters that are too small will cause over-firing, an undesirable operating condition. Over-firing is when the burner operates at a higher rate than the design capacity of the heater for extended periods in an attempt to maintain needed temperatures. Over-firing decreases efficiency and increases the film temperature of the thermal fluid, which shortens its life.
The reverse will happen when the heater is too large. It may constantly cycle on and off. Its run cycle may be too short for maximum efficiency. However, aside from the extra cost of the heater, moderate over-sizing is not a problem for hot oil heaters with fully-modulating burners. Fully-modulating burners can normally fire at a rate low enough to reduce frequent on-off cycling. Even so, hot oil heaters should not be grossly oversized.

← previous page next page →
|
|